Laporan Perkembangan Projek UKM-Maxis (05/02/2016)

Laporan status pemasangan AP 5 Februari 2016

SitesStatusRemarks
Kolej Burhanuddin HelmiCompleted •        Trouble shooting and fine tuning in progress.
Kolej Aminuddin Baki•        To be completed by February 15th
Kolej Keris Mas•        Around 10% of installed AP affected.
Kolej Ibu Zain•        Any AP relocation due to none-coverage from tenant, shall be done in the 4th week of February
Kolej Rahim Kajai
Kolej Dato Onn
Kolej Ibrahim Yaakob (KIY)
Kolej Tun Hussein Onn (KTHO)
Kolej Tun Syed Nasir (KTSN)Work in progressAP required – 55 units
·        Feb 10th – 45 AP on air , 5 AP to be installed by Feb 12 th
·        Target full completion – Feb 12th
Kolej Tun Dr Ismail 1 (KTDI 1)Work in progressAP required – 45 units
• January 21st – start work
• February 28th – Full completion
• Fiber from Kolej to PPUKM to be done on Feb 13th
Kolej Tun Dr Ismail 2 (KTDI 2)Work in progressAP required – 25 units
•        January 21st – start work
•        All 25 AP installed. Fiber splicing in progress
•        February 12 th – Full completion