Laporan Perkembangan Projek UKM-Maxis (05/02/2016)
Laporan status pemasangan AP 5 Februari 2016
Sites | Status | Remarks |
---|---|---|
Kolej Burhanuddin Helmi | Completed | • Trouble shooting and fine tuning in progress. |
Kolej Aminuddin Baki | • To be completed by February 15th | |
Kolej Keris Mas | • Around 10% of installed AP affected. | |
Kolej Ibu Zain | • Any AP relocation due to none-coverage from tenant, shall be done in the 4th week of February | |
Kolej Rahim Kajai | ||
Kolej Dato Onn | ||
Kolej Ibrahim Yaakob (KIY) | ||
Kolej Tun Hussein Onn (KTHO) | ||
Kolej Tun Syed Nasir (KTSN) | Work in progress | AP required – 55 units |
· Feb 10th – 45 AP on air , 5 AP to be installed by Feb 12 th | ||
· Target full completion – Feb 12th | ||
Kolej Tun Dr Ismail 1 (KTDI 1) | Work in progress | AP required – 45 units |
• January 21st – start work | ||
• February 28th – Full completion | ||
• Fiber from Kolej to PPUKM to be done on Feb 13th | ||
Kolej Tun Dr Ismail 2 (KTDI 2) | Work in progress | AP required – 25 units |
• January 21st – start work | ||
• All 25 AP installed. Fiber splicing in progress | ||
• February 12 th – Full completion |